AIA A701 Instruction
GC Exam-AIA A701 Instructions to Bidders
Question | Answer |
---|---|
The proposed contract document consist of the form of agreement between the owner and the contractor? | Conditions of the contract, drawings, specifications, and all addenda issued prior to the execution of the contract |
The bidder represents? | The bidder represents that the bidder has visited the site and has become familiar with the conditions under which the work is to be preformed |
The bidder shall carefully study and compare the bidding documents with each other and with the work being bid concurrently or presently under construction to the extent that it relates to the work for which the bid is submitted | The bidder shall carefully study and compare the bidding documents with each other and with the work being bid concurrently or presently under construction to the extent that it relates to the work for which the bid is submitted |
No substitutions will be considered prior to the receipt of bids unless written request has been received by the architect at least ____ days prior to the date for receipt of bids? | at least 10 days |
Addenda will be issued no later than ___ days prior to the date for receipt of bids? | 4 days |
The owner shall at the request of the bidder submit reasonable evidence that the owner has made arrangements to fulfill his financial obligations no later than ____ days prior to the expiration date for the withdrawal of bids? | 7 days |