Construction Processes.

Quiz yourself by thinking what should be in each of the black spaces below before clicking on it to display the answer.
        Help!  

Question
Answer
show SSSSDIMFF. = stable. supported safe access and exit stop logs. dewatered if necessary Inspected daily before each shift May be a confined space (gas detection needed). fenced off properly (falls from height) formation need protection from weather  
🗑
Traditional Procurement, who is the contract between.   show
🗑
show Trial Pits shell and Auger Rotary Borehole Rotary Borehole is used in rock or very hard materials.  
🗑
Disadvantages of using Sheet Piles.   show
🗑
show Secant Piling have interlocking piles. Secant Piling retains water much better.  
🗑
Normal methods for excavating rocks.   show
🗑
show Work should be regulated Risk Assessment must be carried out by designers and contractors.  
🗑
show Work should be regulated. Risk assessment must be carried out by designers and contractors.  
🗑
show Because they allow for uncertainty in the design process. or Because they provide a design margin over the theoretical design capacity.  
🗑
list 6 items to check when pouring a re- inforced concrete foundations.   show
🗑
show How long to make them. (i.e. knowing what length to make them is a design issue) Solution would be to use segmental piles 2 to 5 metres in length.  
🗑
show Expansion Joints - Designer Contraction Joints - Designer Construction Joints - Contractor.  
🗑
show Mix Design. Types of release agents. limitations on size of form-work type and position of Construction Joints. Deflection Limits for the formwork Type of finish required for all formed surfaces. Method of Sealing the form surfaces.  
🗑
Long term staining or spalling of concrete is caused by   show
🗑
show They are taken for 6 months to see if there are any changes in the groundwater levels, this is then used for designing de-watering methods of excavations.  
🗑
show Sump Pumping Well Point System.  
🗑
show Excavating Slurry trenches. Diaphragm walls, Pressure grouting  
🗑
show Spilling of concrete could create slippery surface Alkaline could come in contact with eyes or skin. Moving skip could hit workers.  
🗑
show Environment, protected species archaeology & historic use Access routes to site Existing Services  
🗑
show Bats Badges Water-voles Reptieles Amphibians Nesting Brids Tree protection Hadgerows Noxious & Invasive Plants  
🗑
Stages Of The Investment Process   show
🗑
show Local Authority Environmental Regulation Health & Saftey Execitives Water & sewage Provider Heritage Bodies Nature conservation organisations  
🗑
4 Main things that are essential to make a valid contract in UK law   show
🗑
show A Simple collection of Standard Terms Designed for particular type of design or construction  
🗑
show Parties know their risks. Parties understand obligations. It is available to everyone Employers and Employees have certainty.  
🗑
show Notifiable projects are those which last longer than 30 days or involve more than 500 people in construction work.  
🗑
Describe the role of the C.D.M CO-ordinator.   show
🗑
show To plan, manage and co-ordinate Health and Safety while construction work is being undertaken.  
🗑
show Ground water could make our structures float. Danger of drowning. It could cost money. Flood our excavations/trenches/pits.  
🗑
On a Drawing of a tank, you specify the diameter to be 12000 metres, is this a term of the Contract?   show
🗑
Explain the Contractual Purpose of the "Drawing"   show
🗑
You are the Contractor's Project Manager on a new tower block project. What safety provisions would you make for workers Constructing the third floor to prevent "falls from height"   show
🗑


   

Review the information in the table. When you are ready to quiz yourself you can hide individual columns or the entire table. Then you can click on the empty cells to reveal the answer. Try to recall what will be displayed before clicking the empty cell.
 
To hide a column, click on the column name.
 
To hide the entire table, click on the "Hide All" button.
 
You may also shuffle the rows of the table by clicking on the "Shuffle" button.
 
Or sort by any of the columns using the down arrow next to any column heading.
If you know all the data on any row, you can temporarily remove it by tapping the trash can to the right of the row.

 
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how
Created by: frantost
Popular Engineering sets