Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

Const. Industry

revision cards for the Construction Industry exam

QuestionAnswer
Kicker Asmall concrete section part of the base slab used as a starting point for a wall to ensure a perfect and solid connection.
Blinding Means protecting a surface before constructing concrete bases.
Starters transfer the stresses from the base reinforcement to the column reinforcement.
Laps Method of lapping one bar over another to transfer stress through concrete from one bar to another
Soffit the underside of a slab for a ceiling.
Construction Joint A joint formed to allow a break in concreting operations.
Kent-ledge Concrete Kent-Ledge blocks are used to act as ballast weights for cantilever towers.
Cover protects the reinforcement with a layer of concrete.
Stop-end Temporary form-work for construction joints.
Shape Code Codes used to identify the shapes of re-inforcement bars.
Spacer Used to provide the correct cover for the reinforcement steel bars used in concrete.
Chair used for supporting concrete reinforcement mats.
C.D.M. Construction Design and Management. This regulations apply to most Common Building projects.
RIDDOR The Reporting of Injuries, Diseases, and Dnagerous Occurences Regulations ( 1995).
Notifiable Projects Construction projects
Hazard this is something with the potential to cause harm.
P.P.E Personal Protective Equipment.
Shell and Auger Site investigation methods used in most materials except rocks. They are used to carry out In- Situ Tests on various soil samples.
S.P.T This test measures the resistance of a soil to the penetration of a split barrel sampler driven into the bottom of a borehole.
U100 Test used for obtaining undisturbed samples in most soils and some weak rocks such as marl and chalk.
Tendering This is the process by which contractors bids are invited, based on the Employers Contract Documents.
Party to Contract Anyone with rights or obligations under the Contract.
Stakeholder Those with an interest and those affected or influenced by the Project.
Replacement Pile Pile with replaces soil with concrete and reinforcement
Displacement Pile Pile which displaces soil as it is driven into the ground.
Well-Point Dewatering This is a process of temporary lowering the ground water in a localized area to accomplish the construction of any below ground project
Differential Settlement This is a slab that does not settle properly due to the compression of the soil beneath the slab.
Risk This is the likelihood of an outcome that deviates from the expected outcome. Risk can be positive or negative outcomes.
Core Sample Undisturbed samples of soils.
Rotary Borehole Used to take core samples in rocks or hard materials.
Trench Sheeting A method of Excavation Support used to support earth banks for the safety of construction workers.
Sheet Piling Steel sheets driven into the ground to provide temporary supports for deep excavations.
Caisson Water tight chamber for working under-water.
Design and Build Strategy A strategy where the Employer employs the Contractor, and the Contractor then employs the Designer and the Sub Contractor.
Standard form of Contract A contract agreement and set of clauses for the conditions of contract, which are filled in and adapted as required for any particular work in hand
Live Load Weight applied to the structure.
Dead Load Weight of the structure itself.
Site Investigation These are the various works undertaken at various stages of the investment process.
Created by: frantost
Popular Engineering sets

 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards