ENGR-502 Mod 11 Test

Enter the letter for the matching Answer
incorrect
1.
The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource.
incorrect
2.
XYZ has 1 workstation making drawings their clients study before accepting XYZ's bid. XYZ has 3 proposals & knows it'll need to use it. Resources used after the workstation are less critical & aren't viewed w/ same reverence as workstation.
incorrect
3.
The root cause of overinflated time estimates is a lack of trust within the project organization.
incorrect
4.
All of these happen during the sprint phase EXCEPT:
incorrect
5.
ABC has 1 workstation that's able to make drawings that clients study before accepting ABC's bid. ABC has 3 proposals & knows which project will be most & least profitable. It's scheduled so most profitable project's work is 1st & least profitable last.
incorrect
6.
The first step in TOC methodology is to:
incorrect
7.
According to CCPM:
incorrect
8.
The sprint portion of the Agile Project Management process is targeted to last:
incorrect
9.
The waterfall project development process is well-suited for instances where:
A.
time constraints exist
B.
sprint goal modification
C.
subordinating a system.
D.
False
E.
the primary causes of inaccurate duration estimation are behavioral in nature.
F.
2.5 plus or minus 1.5 weeks
G.
exploiting a constraint.
H.
True
I.
identify the constraint.
Type the Answer that corresponds to the displayed Question.
incorrect
10.
Traditional, highly structured approaches to planning and managing projects are recognized as being less effective for _______ than Agile Project Management.
incorrect
11.
Once the organization elevates its constraint, its system has no constraint.
incorrect
12.
In order to estimate completion of a Gaussian, or lognormal, distributed activity time with a 90% or higher degree of confidence, the time may be overestimated by as much as:
incorrect
13.
5 members of a team +20% to individual serial activities & submit time estimates to manager. Manager sums activity length & +20% for personal safety margin. He adds 20% to final estimate. Top mgmt doesn't cut. How much of a cushion is built in project?
incorrect
14.
Which adjective is most appropriate for Agile Project Management ?
incorrect
15.
An important element in critical chain scheduling is to change from a late-finish (procrastination) approach to an early-start approach.
incorrect
16.
The critical chain is usually the same as the critical path.
incorrect
17.
In Agile Project Management, a sprint backlog is essentially a:
incorrect
18.
In Agile Project Management, the term "scrum" refers to:
incorrect
19.
The best thing a project manager can do when noticing common cause variation in a project's monthly budget summary is to: