ENGR-502 Mod 11
ENGR-502 Exam II
Question | Answer |
---|---|
Once the organization elevates its constraint, its system has no constraint. | False |
The root cause of overinflated time estimates is a lack of trust within the project organization. | True |
The Central Limit Theorem states that if a number of probability distributions are summed, the variance of the sum equals the sum of the variances of individual distributions. | True |
An important element in critical chain scheduling is to change from a late-finish (procrastination) approach to an early-start approach. | False |
The critical chain is usually the same as the critical path. | False |
The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource. | False |
The first step in TOC methodology is to: | identify the constraint. |
ABC has 1 workstation that's able to make drawings that clients study before accepting ABC's bid. ABC has 3 proposals & knows which project will be most & least profitable. It's scheduled so most profitable project's work is 1st & least profitable last. | exploiting a constraint. |
XYZ has 1 workstation making drawings their clients study before accepting XYZ's bid. XYZ has 3 proposals & knows it'll need to use it. Resources used after the workstation are less critical & aren't viewed w/ same reverence as workstation. | subordinating a system. |
The best thing a project manager can do when noticing common cause variation in a project's monthly budget summary is to: | do nothing. |
According to CCPM: | the primary causes of inaccurate duration estimation are behavioral in nature. |
In order to estimate completion of a Gaussian, or lognormal, distributed activity time with a 90% or higher degree of confidence, the time may be overestimated by as much as: | 200%. |
5 members of a team +20% to individual serial activities & submit time estimates to manager. Manager sums activity length & +20% for personal safety margin. He adds 20% to final estimate. Top mgmt doesn't cut. How much of a cushion is built in project? | 73% |
Which adjective is most appropriate for Agile Project Management ? | iterative |
Traditional, highly structured approaches to planning and managing projects are recognized as being less effective for _______ than Agile Project Management. | software development |
The waterfall project development process is well-suited for instances where: | time constraints exist |
The sprint portion of the Agile Project Management process is targeted to last: | 2.5 plus or minus 1.5 weeks |
In Agile Project Management, the term "scrum" refers to: | a meeting |
In Agile Project Management, a sprint backlog is essentially a: | punch list |
All of these happen during the sprint phase EXCEPT: | sprint goal modification |