Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

MGMT 418 Lesson 2

MGMT 418 Lesson 2 - Project Scheduling

QuestionAnswer
Activity A distinct, scheduled portion of work performed during the course of a project” (PMBOK 2013). An activity consumes resources and takes time to complete. An activity is where project performance is determined. Throughout this course, activity and task will be used interchangeably
Project Network Diagram A graphical representation of the logical relationships among the scheduled activities.
Path A sequence of activities in a schedule network that starts from the beginning of a project to the end of the project.
Event Some particular point in time that is often determined by the result of completing one or more activities.
Node One of the defining points of a network; a junction point joined to some or all of the other dependency lines (paths).
Predecessors Those activities that must be completed prior to initiation of a later activity in the network.
Successors Activities that cannot be started until previous activities have been completed. These activities follow predecessor tasks.
Merge Activity An activity that has more than one immediate predecessors.
Burst activity An activity that has more than one immediate successors.
Serial Activities Those that flow from on to the next, in sequence.
Concurrent Activities When the nature of the work allows for more than one activity to be accomplished at the same time, these activities are called concurrent, and parallel project paths are constructed through the network.
Early Start (ES) date The earliest possible point in time when an activity can start. ES = max value of the EF dates of the predecessors.
Early finish (EF) date The earlies possible point in time when an activity can finish. EF = ES + Activity duration
Late finish (LF) date The latest possible point in time when an activity can finish without delaying the project completion date. LF = min value of the LS dates of the sucessors
Late start (LS) date The latest possible point in time when an activity can start without delaying the project completion date. LS = LF - Activity duration
Forward Pass A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or given point in time. An additive move through the network from start to finish
Backward Pass A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date. A subtractive move through the network from finish to start.
Float The amount of time an activity may be delayed from its early start without delaying the finish of the project. Float is also called slack: (LS - ES) or (LF - EF).
Critical path The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
Critical Path Method A network analysis technique used to determine the amount of schedule flexibility on logical network paths in the project schd network and to determine min project duration.
Resource-limited schedule A project schedule that is adjusted based on the availability and constraints of resources.
Resource Constraints This refers to the limited availability of resources, such as manpower, equipment, budget, or materials.
Resource Leveling Technique used to address the over-allocation of resources. By rescheduling tasks that are flexible in terms of start and end times, project managers aim to smooth out the demand for resources, ensuring that they are used efficiently and consistently.
What are five key points to Resource-limited schedule 1. Resources Constraints 2. Potential Delays 3. Resource Leveling 4. Critical Path Changes 5. Priority Systems
Activity on Arrow (AOA) AOA network diagram, is a graphical representation used to depict the sequence of activities in a project.
Activity on Node (AON) AON Network diagram, is another type of graphical representation used to illustrate the sequence of activities in a project with nodes or boxes and lines between them.
Three - Point Estimating Technique Method used to estimate the duration or cost of an activity in project management. It draws on the concept of the Program Evaluation and Review Technique (OERT) and involves the use of three estimates to define an approximate range for an activity's duration.
What 3 estimates are used to improve the accuracy and realism activity time and cost estimates in the Three point estimate method Most optimistic (a) , most likely (m) , most pessimistic (b)
What is the formula for finding time Estimate Activity Duration = TE = a + 4m +b / 6
What are the advantages of Three-Point Estimating Range of Estimates: Provides a range of possibilities that can be useful for risk management Flexibility: offers a balanced view by considering both best-case and worst-case scenarios More accurate: By considering three potential outcomes, if often yields a more realistic estimate than if only a single point was considered.
What are the limitations of Three-Point Estimating Requires More Info: This technique requires detailed information and can be time-consuming. Subjectivity: The estimates, especially the optimistic and pessimistic ones, can be influence by the estimator's biases or risk preferences.
What are the 6 steps of the CPM 1. Develop a network diagram. 2. Estimate the activity durations 3. Forward Pass 4. Backward Pass 5. Calculate Floats (slacks) 6. Determine the critical path and critical activities
What does a network diagram do? Shows all activities in a project and the work sequences between them.
What is Forward pass formulas? ES = max value of the EF dates of its predecessors EF = ES + Activity duration
What is Backward pass formulas? LF = min value of the LS dates of its successors LS = LF - Activity duration
What does floats/slacks show? the amount of time that an activity can be delayed without delaying the project completion date
What are float/slack formulas? Float/Slack = LS - ES or Float/Slack = LF - EF
Popular Miscellaneous sets

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards