| Question | Answer |
|---|---|
| The project control cycle is continuous. | True |
| Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals. | True |
| The classic S-curve is a plot of cumulative cost versus elapsed time in weeks. | True |
| Since a project may get ahead of or fall behind schedule, a calendar date cannot be a milestone. | False |
| The one factor that earned value management considers that an S-curve does not include is performance. | True |
| The schedule performance index is the ratio of the actual cost to the earned value. | False |
| The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages. | False |
| A project manager needs the work breakdown structure and a time-phased project budget to establish the project baseline. | True |
| Your organization started a project; nothing you have attempted before comes close to many of the activities that are necessary to complete this project. Your earned value mgmt should trackeclosely with a % complete rule in increments of 5 -10% | False |
| The project implementation profile assesses the performance of the project team with respect to 10 critical success factors and can be used on an ongoing project. | True |
| Project goal setting includes setting a baseline plan, which is predicated on: | an accurate work breakdown structure. |
| Measurement mechanisms should include a clear definition of: | what to measure. |
| If significant deviations from the project plan are detected, corrective action is taken and then: | the monitoring and control cycle begins anew. |
| The classic project S-curve is a plot of: | money expended versus elapsed time. |
| An S-curve CANNOT be used to: | determine the cause of positive variance. |
| An excellent way to coordinate schedules with vendors and suppliers is through the use of: | milestones. |
| A tracking Gantt chart: | identifies the stage of completion for each task. |
| It is possible to measure: | both positive and negative deviations from the schedule baseline with the tracking Gantt chart. |
| Earned value management is also known as: | earned value analysis (EVA). |
| Which of these tools allows a project team to make future projections of project status based on its current state? | earned value management |