Planning Tools
Robbins & Coulter 11th Edition
| Question | Answer |
|---|---|
| Environmental scanning | the screening of large amounts of information to anticipate and interpret changes in the environment |
| Competitor Intelligence | environmental scanning activity by which organizations gather information about competitors |
| Forecasts | predictions of outcome |
| Budget | a numerical plan for allocating resources to specific activities |
| Scheduling | detailing what activities have to be done, the order in which they are to be completed, who is to do each, and when they are to be completed |
| Gantt Chart | a scheduling chart developed by Henry Gantt that shows actual and planned output over a period of time |
| Load chart | a modified Gantt chart that schedules capacity by entire departments or specific resources |
| PERT network | a flowchart diagram showing the sequence of activities needed to complete a project and the time or cost associated with each |
| Events | end points that represent the completion of major activities in a PERT network |
| Activities | the time or resources needed to progress from one event to another in a PERT network |
| Slack time | the amount of time an individual activity can be delayed without delaying the whole project |
| Critical path | the longest sequence of activities in a PERT network |
| Breakeven analysis | a technique for identifying the point at which total revenue is just sufficient to cover total costs |
| Linear programming | a mathematical technique that solves resource allocation problems |
| Project | a one-time-only set of activities that has a definite beginning and ending point in time |
| Project management | the task of getting a project’s activities done on time, within budget, and according to specifications |
| Scenario | a consistent view of that the future is likely to be |