Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password

Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.

Overview and Revision

Quiz yourself by thinking what should be in each of the black spaces below before clicking on it to display the answer.
        Help!  

Question
Answer
Definitions – Clause 2   show
🗑
show Cash retention or bank guarantee or insurance bond etc  
🗑
Security – Clause 5 - Limits only apply to ‘building work’ under QBCC Act   show
🗑
Security – Clause 5 - Limits only apply to ‘building work’ under QBCC Act   show
🗑
show e.g. 2% BG plus 3% cash retention, not 5% BG plus 5% cash retention  
🗑
Security – Clause 5 - Subcontractor can replace cash retention with other form of security   show
🗑
Security – Clause 5 - Recourse to security   show
🗑
Security – Clause 5 - Release of security   show
🗑
show Super directs how to resolve it and possible variation if cost more / less than what contractor could reasonably have anticipated at time of tendering if it is in a principal supplied document  
🗑
show Both principal and contractor must supply one electronic copy of its documents unless contract says otherwise  
🗑
Contract Documentation – Clause 8 - Must understand all documents that form part of the Contract   show
🗑
Assignment & Subcontracting (cl 9) - Requirements and obligations on both parties   show
🗑
show check the contract  
🗑
show ‘building work’ and check ABN to confirm legal entity being contracted  
🗑
Assignment & Subcontracting (cl 9) - Understand that head contractor is always liable for actions of all subbies   show
🗑
Assignment & Subcontracting (cl 9,10) - Understand difference between nominated subcontractor and selected subcontractor and how it affects the contract   show
🗑
show - BUT principal is not responsible for actions of subcontractors even if nominated or selected subcontractor - Understand rights of subcontractors if not paid by head contractor  
🗑
Provisional Sums – Clause 11 - What is a provisional sum?   show
🗑
show - priced under cl 40.5 - includes P&OH on provisional sum work  
🗑
Provisional Sums – Clause 11 - Why use a provisional sum?   show
🗑
show Physical condition that could not be reasonably have been anticipated at time of tender/contract despite examination and inspection  
🗑
Site Conditions – Clause 12 - What is a latent condition? - Doesn’t cover change in design – only a change to something physical like rock underground if soil test didn’t encounter   show
🗑
show Not a weather condition or physical condition that is a consequence of a weather condition  
🗑
Site Conditions – Clause 12 - Requirements and obligations of both parties - Contractor must notify with “Early Warning” Notice as soon as possible but no later than 1 BD of becoming aware of LC and, where possible, before disturbing LC –   show
🗑
show - Superintendent must direct what to do - Entitled to variation if incur extra costs due to LC - Entitled to EOT if cl 35.3 permits it - not entitled to costs incurred more than 5 BD before notifying super of LC  
🗑
Site – Clause 27 - Possession of Site   show
🗑
show Contractor has possession of site but must allow reasonable access for principal and other contractors of the principal  
🗑
Site – Clause 27 - Discovery of items of value   show
🗑
show Site can only be used for purposes of carrying out the WUC  
🗑
Materials & Work – Clause 30 - Quality of Works   show
🗑
Materials & Work – Clause 30 - Defective Works (1)   show
🗑
show Principal can engage another contractor to rectify and recover cost from contractor if contractor fails to rectify as soon as practicable. Cannot happen without prior written notice of this possible action and at least 10 BD have passed from notice  
🗑
show Contractor may request principal to accept defective work – contract sum adjusted to reflect change in value of the Works and any loss suffered by P  
🗑
Progress & Programming – Clause 33 - Construction program (1)   show
🗑
show - Contractor must revise program to reflect actuals and critical path - used for EOT claims i.e. delay must be a delay on critical path on program (cl 35.3(a)(iii))  
🗑
Progress & Programming – Clause 33 - Rate of progress   show
🗑
Progress & Programming – Clause 33 - Acceleration - Super may notify contractor of proposal to accelerate WUC - Contractor must provide info in cl 40.2(a) for proposed variation   show
🗑
Suspension – Clause 34 (1)   show
🗑
Suspension – Clause 34 (2)   show
🗑
Times for Commencement and PC – cl 35 - Understand different contractual milestones   show
🗑
Times for Commencement and PC – cl 35 - Commencement   show
🗑
show - In NCW4, NOD is a precondition to an EOT i.e. if don’t give NOD, not entitled to EOT  
🗑
Times for Commencement and PC – cl 35 - Extensions of time claims (1)   show
🗑
Times for Commencement and PC – cl 35 - Extensions of time claims (2)   show
🗑
Times for Commencement and PC – cl 35 - Liquidated damages   show
🗑
show - Only if EOT is granted - Only for some causes of delay  
🗑
show Delay costs rate is determined from Annexure B Commercial Framework or if not included in Annexure B, valued by superintendent to cover reasonable additional costs but not profit, loss of profit or loss of opportunity  
🗑
show - Commences 4pm on date of PC - Ends on last day of period noted in Annexure A (typically 12 mths) - Contractor must rectify defects notified to it ASAP at its own cost - Superintendent may direct contractor to commence and complete by specified dates  
🗑
Defects Liability Period – cl 37 - Defects Liability Period: (2)   show
🗑
show Any change whatsoever to the contract whether incurs additional cost or not  
🗑
Variations – Clause 40 - Proposed variations   show
🗑
show - Pricing of vars by cl 40.5 in order of precedence - Entitled to P&OH if it is for additional WUC  
🗑
Variations – Clause 40 - Variations for convenience of contractor   show
🗑
Variations – Clause 40 - Valuation of variations & BOQs   show
🗑
show If contractor believes it received a direction for variation from super, must notify superintendent within 5 BD of receipt of direction  
🗑
show - May be claimed at date in the month or stages of WUC stated in Annexure A - Must give all items listed in contract with each payment claim  
🗑
Certificates & Payments – Clause 42 - Responding to payment claim   show
🗑
Certificates & Payments – Clause 42 - Times for payment   show
🗑
Certificates & Payments – Clause 42 - Unfixed plant and materials   show
🗑
show - Payment is on account and is not evidence of value of work carried out  
🗑
show - contractor must give super 10 BD prior notice of when expect to reach PC. - Super inspects the works and must give a Certificate of PC or reasons why it doesn’t within 10 BD of receipt of contractor’s notice  
🗑
show - standard form NCW4 requires “Final Payment Claim” at PC which is not typical. The Final Claim would typically be permitted at end of DLP - in NCW4, Final Payment Claim must include all moneys contractor believes it is entitled to under the contract  
🗑
show - Must be given by super within 10 BD after receipt of Final Payment Claim - Is conclusive evidence of final financial position under the contract except disputes  
🗑
Certificates & Payments – Clause 42 - Certificate of Final Completion - typically evidence final position between the parties except for fraud, dishonesty, things that couldn’t be seen at end of DLP etc   show
🗑
Bill of Quantities - Annexure B - Different alternatives can apply   show
🗑
Bill of Quantities - Annexure B - Understand when to apply the limit of accuracy (to Schedule of Rates)   show
🗑
show Priced BOQ must equal contract price  
🗑
Bill of Quantities - Annexure B - Errors in BOQ   show
🗑
show - Managing contractor (e.g. DEPW) - Project management contracts (AS4915-2002) - Construction management contracts (AS4916-2002) - Construction management trade contracts (AS4917-2003)  
🗑
show - Design – Construct – Maintain (DCM) - Engineering – Procurement – Construct (EPC) - Engineering – Procurement – Construction Management (EPCM)  
🗑
Relationship Contracts - Project Delivery Methods   show
🗑
Procurement -   show
🗑
show Sets out how the tender documents are to be prepared, how the tender process is to be set up and applied, how the tenders are to be processed and how feedback is to be given to all tenderers  
🗑
Procurement - Tendering - Tendering Code (AS4120) - What are the main objectives?   show
🗑
Procurement - Tendering - Tendering Code (AS4120) - Roles and responsibilities   show
🗑
BIF Act 2017 - Main chapters:   show
🗑
show - Applies to some projects now - Phased rollout – next phase pushed back to April 2025  
🗑
BIF Act 2017 - Progress Payments: - Must understand:   show
🗑
show - who can use it - what happens if you give a subcontractor’s charge after a chapter 3 BIFA payment claim and vice versa  
🗑
BIFA Payment Claims - All payment claims must:   show
🗑
show Other examples: ‘claim’, ‘due date’, ‘payable now’  
🗑
show - ‘Claim 1’ - ‘Completion of works’ - Concrete works (possibly not enough of a description)  
🗑
show - ‘Completion of tiling works to building 3 ground floor’ - ‘Completion of painting works to units 3 and 4’ - ‘landscaping works’  
🗑
Description of the works/services - Describe construction work or related goods and services:   show
🗑
BIFA Payment Claims - Reference Date:   show
🗑
BIFA Payment Claims   show
🗑
Reference Date - Cannot give a claim PRIOR to reference date i.e. early claim is not a valid BIFA payment claim (1)   show
🗑
Reference Date - Cannot give a claim PRIOR to reference date i.e. early claim is not a valid BIFA payment claim (2)   show
🗑
show be given’ = not relevant to a BIFA claim but entirely relevant to a contractual claim. That provision will make an early contractual claim a valid claim but cannot make an early BIFA claim, into a valid BIFA claim  
🗑
show Not good because contract does not ‘state’ a date for when a payment may be claimed because contractor has the power to decide what day the claim will be submitted i.e. any time prior to 20th of each month so default reference date applies  
🗑
show anniversary of the first day that construction work is carried out and every month after that - i.e. if work started on 3rd of the month, then reference date is 3rd of every month  
🗑
show - ‘Claims may be submitted on 25th of each month up to the Date of Practical Completion and at end of the Defects Liability Period’ - ‘Claims may be submitted on the last business day of each month in which work is carried out’  
🗑
show reference date (as long as it is within 6 months of when at least one part of the work was carried out)  
🗑
Payment Claim - Can claim for work carried out up to reference date but not   show
🗑
Payment Claim - If claim for work after reference date, not entitled to   show
🗑
Payment Schedules - Payment Schedule must be given within the earlier of:   show
🗑
show full payment of the amount claimed is made by the Respondent by the Due Date for Payment  
🗑
show - be given to the person who gave the Payment Claim; - be in writing; - refer to the Payment Claim;  
🗑
Payment Schedules - Payment Schedule must: (2)   show
🗑
Payment Schedule Examples - ‘We refer to your payment claim 3 dated 20 May 2024 claiming $45,000 excluding GST. However, we have assessed the payment claim and will be   show
🗑
Due Date for Payment - Due Date for Payment is: (1)   show
🗑
show - exceeds the maximum time for payment under s67U or s67W of the Queensland Building and Construction Commission Act 1991 (QBCC Act); - is a ‘pay when paid’ clause  
🗑
show 10 business days after the Payment Claim was given.  
🗑
show - maximum time for payment of head contracts = 15 business days from receipt of payment claim (s67W) - maximum time for payment of subcontracts = 25 business days from receipt of payment claim (s67U)  
🗑
show Liability to pay depends on payment by someone else e.g. you don’t get paid until I get paid  
🗑
show Due date for payment is dependent on due date for payment under a separate contract e.g. subcontract due date is 10 BD after head contract due date  
🗑
show Liability to pay or due date for payment is dependent on another contract e.g. I’ll return your retention when I get my retention back  
🗑
show means the amount determined and described as such in the Commercial Framework included as Annexure B, subject to adjustment in accordance with the Contract.  
🗑
Contractor =   show
🗑
Date of Acceptance of Tender = means the earlier of:   show
🗑
show b) where another date is determined in any dispute resolution procedure as the date upon which practical completion was reached, that other date.  
🗑
Date for Practical Completion = means:   show
🗑
show means work carried out by the Contractor for which payment is made on the basis of daily time and cost records for labour, plant, materials, services and other items as provided in clause 41.  
🗑
Provisional Sum =   show
🗑
show means the lands and other places to be made available by the Principal to the Contractor for the purpose of executing the Works.  
🗑
show means the person appointed by the Principal to be the Superintendent pursuant to clause 23.  
🗑
Superintendent’s Representative =   show
🗑
Cash retention   show
🗑
show A promise from a bank to cover losses if the contractor defaults  
🗑
An insurance bond (also called a surety bond or contract bond) is a third-party guarantee provided by an insurance company or surety to ensure...   show
🗑


   

Review the information in the table. When you are ready to quiz yourself you can hide individual columns or the entire table. Then you can click on the empty cells to reveal the answer. Try to recall what will be displayed before clicking the empty cell.
 
To hide a column, click on the column name.
 
To hide the entire table, click on the "Hide All" button.
 
You may also shuffle the rows of the table by clicking on the "Shuffle" button.
 
Or sort by any of the columns using the down arrow next to any column heading.
If you know all the data on any row, you can temporarily remove it by tapping the trash can to the right of the row.

 
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how
Created by: Asher - S