CAPM Formulas
Formulas to Know for the CAPM Exam
| Question | Answer |
|---|---|
| [Formula] - Total Float | LS-ES or LF-EF |
| [Formula] - Cost Variance (CV) | EV - AC |
| [Formula] - Schedule Variance | EV - PV |
| [Formula] - Cost Performance Index (CPI) | EV/AC or EV(cum)/AC(cum) |
| [Formula] - Schedule Performance Index (SPI) | EV/PV |
| [Formula] - Estimate at Completion (w/Bottom Up) | AC + Bottom-up ETC |
| [Formula] - Estimate at Completion (w/CPI cumulative) | BAC/CPI(cumulative) |
| [Formula] - Estimate at Completion (w/BAC) | AC + (BAC - EV) |
| [Formula] - Estimate at Completion (w/SPI[cum]) | [AC - (BAC - EV)] / [CPIc x SPIc) |
| [Formula] - To Complete Performance Index (TCPI) | (BAC-EV)/(BAC-AC) |
| [Formula] - Estimate to Complete (ETC) | EAC - AC |
| [Formula] - Variance at Completion (VAC) | BAC - EAC |
| [Formula] - Communication Channels | N(N-1) / 2 |
| [Formula] - Calculate Standard Deviation | [Pessimistic - Optimistic]/6 |