NERC Training
Transmission Operator
| Question | Answer |
|---|---|
| IROL Tv | not to exceed 30 minutes, to get back to within IROL limits violations |
| How much time do you have to notify of voltage regulators limitations, problems from the Generator Operator | 30 minutes |
| Real-time Assessment (i.e. Contingency Analysis) | must be successful at least once every 30 minutes |
| Notify RC of | any planned, or unplanned outages with a duration of 30 minutes or more |
| What is a must have? | a back-up functionality plan Not necessarily a BUCC.TOPO |
| ALL System Operators: RC, TOP, BA notify impacted entities and NERC | • Loss of communication >30 min • Unplanned control center evacuation >30 min • Complete loss of monitoring >30 min • Backup Control Center transfer must be <2 hr; test backup control center must last at least 2 hr |