NERC Training
Recall
| Question | Answer |
|---|---|
| 1% drop in frequency | results in a 2% drop in total load (3% drop in motor load) for Interconnected System |
| 5% decrease in Voltage | results in a 3% decrease in load |
| Disturbance Control Standard (DCS) Compliance | 100% to the 15-minute recovery |
| Control Performance Standard (CPS) compliance >= | 100% monthly |
| BAAL<30 minutes | to be get within bound |
| Manual Load Shed ≥ 100 MW | is reportable |
| Loss of Firm Load ≥ 300 MW | is reportable |
| 6-10% of load shed will increase | Frequency 1 Hz in an Island |
| In restoration | connect 5% of the total synchronized generation of load at one time. |