| Any delay in a zero-float activity will directly result in a delay to what? | the project completion date |
| Activities with zero total float are, by definition, on what? | the critical path |
| what indicates that the early start/finish dates are equal to the late start/finish dates (Late Start - Early Start = 0) | Scheduling constraint |
| Activities with zero float require strict management attention as they are vital to meeting the deadline what is the activites called? | High Priority |
| The activity cannot be delayed without delaying the entire project is called what? | Total Float (0) |
| The activity cannot be delayed without delaying the early start of its successor activity is called what? | Free Float (0) |
| What does the Stakeholder Engagement Assessment Matrix contain? | A document w/the 5 levels of engagement: Unaware, Resistant, Neutral, Supportive, Leading |
| What tool is the Stakeholder Engagement Assessment Matrix found? | Data Representation |
| Where to find the 5 levels of engagement: Unaware, Resistant, Neutral, Supportive, Leading? | the Stakeholder Engagement Assessment Matrix in the Tool Data Representation in the process Plan Stakeholder Management |
| How exactly does this document look that contains the 5 levels of engagement: Unaware, Resistant, Neutral, Supportive, Leading? | A spreadsheet w/columns of stakeholder names & rows w/both Current & Desire listed under 2 of the levels of engagement |