| Question | Answer |
|---|---|
| Discretionary Dependency | a type of dependency that the project manager and project team choose to impose on the project schedule, such as the use f an established corporate practice |
| External Dependency | a relationship between project activities and non-project activities |
| Fast Tracking | a schedule compression technique in which you do activities in parallel that you would normally do in sequence |
| Finish-to-Finish | an activity relationship type that requires the current activity to be finished before its successor can finish |
| Finish-to-Start | an activity relationship type that requires the current activity to be finished before its successor can start |
| Gantt Chart | Graphic display of schedule related information in the form of a bar chart |
| Lag | a modification of a logical relationship that directs a delay in the successor activity |
| Lead | a modification of a logical relationship that allow an acceleration of the successor activity |
| Mandatory Dependency | a type of dependency where the relationship between two tasks is created by the type of work the project requires |
| Network Diagram | a graphical representation of the logical relationship among the project schedule activities |