Save
Upgrade to remove ads
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

EGB482 (Week 6)

Construction Contract models and tendering

QuestionAnswer
Various contracting models for construction projects - Traditional/adversarial contracting 1Construct-only 2Design & construct 3Managing contractor 4Construction management 5Design, Build, Operate (DBO) 6Design, Build, Operate, Maintain (DBOM) 7Build, Own, Operate (BOO) 8Build, Own, Operate, Transfer (BOOT) 9Public Private Partnerships (PPP)
Various contracting models for construction projects - Fast-track contracting - Engineer, Procure, Construct (EPC) - Engineer, Procure, Construction - Management (EPCM)Cost Plus - Early Contractor Involvement (ECI)
Various contracting models for construction projects - Relationship contracting - Partnering - Alliance contracting - Collaborative contracting
What is the difference between the contracting models? - What work or services is the contractor being asked to perform? - How will the contractor get paid for doing the work or services? - What risks will the contractor be expected to carry?
Traditional contracting - Construct-only contract - Building to a design supplied by the principal - Using materials specified by the principal or its design consultant - Choosing subcontractors - Appointing subcontractors - Often fixed price - Responsible for construction to meet principal’s design and specification
Traditional contracting - Design & construct contract - Detailed design and engineering - Specifying materials - Building - Choosing subcontractors - Appointing subcontractors - Often fixed price - Responsible for design and construction to meet principal’s project requirements
Fast-track contracting - Engineer, procure & construct contract (EPC) - Detailed design and engineering - Specifying and procuring materials - Choosing and appointing subcontractors - Often fixed price - Full turnkey responsibility
Fast-track contracting - Engineer, procure and construction management (EPCM) (1) - Detailed design and engineering - Specifying materials - Managing tender process for procuring materials and work package contractors / trade contractors (on behalf of principal) - Project management and administration of work package contracts
Fast-track contracting - Engineer, procure and construction management (EPCM) (2) - Usually paid on cost-reimbursable basis - Responsible for the work it directly carries out, including managing work package contractors, but not responsible for their work or for the project meeting schedule or budget
Fast-track contracting for energy & resources major projects Feasibility study => Front end engineering design (FEED) => EPCM /EPC
Relationship contracting - Partnering - Overarching agreement between principal and contractor to work together on a collaborative basis - May have a variety of individual contracts between them
Relationship contracting - Alliancing Contractual for a project sets out shared approach to risks
Relationship contracting - Collaborative contracting Various approaches – may include more traditional contracts with a collaborative overlay
The organisation Standards Australia produces a variety of documents, including standard specifications and procedures - Example: AS5100.1:2017 – Bridge design, Part 1: Scope and general principles
Example: AS5100.1:2017 – Bridge design, Part 1: Scope and general principles - The Standards Australia website says: • On their own, standards are voluntary. There is no requirement for the public to comply with standards. However, State... and Commonwealth governments often refer to Australian Standards® (AS) or joint Australian/New Zealand Standards (AS/NZS) in their legislation. • When this happens, these standards can become mandatory
Standards Australia also publishes standard forms of contract - Example: AS4902-2000 – General conditions of contract for design and construct
Standards Australia also publishes standard forms of contract - These are voluntary – a person who needs to choose a form of contract to use for a project can... choose to use the most suitable Australian Standard contract, or a completely different standard form of contract, or write one specifically for the project
Popular Australian Standards Contracts - AS4000-1997 •For major works, for construct-only delivery •Suitable for a wide range of electrical, civil and mechanical engineering, as well as building, contracts, where a ‘superintendent’ is engaged to administer the contract •Updates AS2124, but some prefer to use the old version
Commonly used international standard forms of contract for civil and process engineering - International Federation of Consulting Engineers (FIDIC) forms “rainbow suite” • FIDIC 2017 Red Book – Construction contract • FIDIC 2017 Yellow Book – Plant & Design-Build contract • FIDIC 2017 Silver Book – EPC/Turnkey Contract • FIDIC 2019 Emerald Book – Conditions of contract for underground works
Commonly used international standard forms of contract for civil and process engineering - New Engineering Contract (NEC4 2017) A series of contracts designed to manage a project, particularly a civil engineering project, from start to finish, with the aim of preventing costly disputes
Role of the contract administrator The contract administrator plays a central role in the administration of the construction contract
The contract administrator may be referred to as: • Superintendent • Engineer • Architect
The more detailed wording in clause 23 of AS 2124 helps us to interpret what is meant by... “reasonably and in good faith” in clause 20 of AS 4000 and AS 4902
AS 2124 – 1992 - The Principal shall ensure that at all times there is a Superintendent, and that in the exercise of the functions of the Superintendent under the Contract, the Superintendent: acts honestly and fairly; Acts within the time prescribed under the Contract or where there is no time prescribed within a reasonable time; and Arrives at a reasonable measure or value of work, quantities or time (cl 23)
AS 4000 – 1997 & AS 4902 - 2000 The Principal shall ensure that at all times there is a Superintendent, and that the Superintendent fulfils all aspects of the role and functions reasonably and in good faith (cl 20)
Contract administrator wears two hats - Contract administrator may carry out two distinct sets of duties – those as principal’s agent and those as a certifier
Contract administrator wears two hats - At common law: • When carrying out duties as principal’s agent, the contract administrator is permitted to act in the interests of the principal • When carrying out duties as a certifier, common law has shown that the contract administrator has a duty to act “fairly and justly and with skill to both parties to the contract” (Pernini Corp v Commonwealth of Australia [1969])
Contract administrator wears two hats - Some standard forms require the contract administrator to act... impartially when carrying out all duties under the contract (AS4000 & AS4902, clause 20)
Contract administrator’s two hats - Principal’s agent - Direction to clarify discrepancies in contract documents - Direction to rectify defective work - Direction to suspend carrying out the work under the contract - Direction to vary the work under the contract
Contract administrator’s two hats - Certifier - Assessing payment claims and issuing payment certificates - Assessing and directing extensions of time - Valuing or pricing variations - Deciding when to issue certificates of practical completion and final completion
Contract administrator’s balancing act - The contract administrator owes legal liability to the principal in his or her contract (contract of appointment) - Does the superintendent owe legal liability to the contractor?
Independent certifier - Duty to act impartially - Duty of care?
Agent of the Principal - Paid by Principal - Expectations from Principal - Representing Principal's interests?
The tender process is the most common method of... procurement for construction projects, particularly large or government projects
Some private organisations may award work on a sole source basis, but even private companies generally want... to get the lowest price possible, and that is hard to verify without getting prices from a number of contractors
Local Government Regulation 2012, Chapter 6 – Contracting - Default approach - Obtain written quotes for medium-sized contractual arrangement contract value more than $15,000 but less than $200,000 in financial year or over proposed term
Local Government Regulation 2012, Chapter 6 – Contracting - Default approach - Invite written tenders for large-sized contractual arrangements • contract value $200,000 or more in financial year or over proposed term • but various exceptions apply • can issue invitation to tender or start with invitation for expressions of interest, create shortlist and then invite written tenders from shortlist
State government procurement - Qld government uses several methods for procurement of goods and services, including (1) • Ad-hoc purchasing • Open tender (all interested suppliers may submit an offer) • Selective tender (suppliers meeting pre-established criteria are invited to offer)
State government procurement - Qld government uses several methods for procurement of goods and services, including (2) • Limited tender (agency invites suppliers of its choice to offer) • Lists of preferred suppliers • Supplier procurement arrangements (standing offer arrangements)
State government procurement - Each department or agency will generally have its own... policies guiding when it will use each method of procurement
Commonwealth Procurement Rules 2024 Division One: Rules for all procurements Section 9.1: Australian Government procurement is conducted by open tender or limited tender
Principal releases Invitation to Tender Invitation to treat for contract to carry out work
Tenderers submit Tenders Offer
Principal evaluates Tenders Offer remains open for acceptance during this period
Principal accepts a Tender Evaluation and tender process concluded Acceptance = Contract formed for carrying out the work
Requests for suppliers or contractors to submit tenders are an... invitation to people to submit tenders
An offer is made by a tenderer when... submitting a tender
Person calling for tenders can choose to accept or... reject the offer
Generally, requests of invitations to tender will be an... invitation to treat
But, it depends on the terms of the request for tenders – sometimes it can be more than that
Principal releases Invitation to Tender for a package of work - Invitation to treat for contract to carry out work - The tender documents may also be an Offer to conduct a tender process on specified terms and conditions
Tenderers submit Tenders to carry out that package of work - Offer to carry out the package of work - If the tender documents are an offer to conduct a tender process, the tender is the Acceptance of the offer to conduct a tender process
Principal evaluates Tenders - Offer remains open for acceptance during this period - If there is a tender process contract, the parties perform their obligations under the tender process contract
Principal accepts a Tender - Evaluation and tender process concluded - Acceptance = Contract formed for carrying out the work - If there was a tender process contract, it has come to an end – all obligations have been performed
How should a tender process be conducted? (1) - Set out a fair process in the tender documents and follow the process in the evaluation stage - Only make a firm commitment to a particular process if that process will definitely be followed
How should a tender process be conducted? (2) - Do not bind yourself to doing something you may not wish to do, and do not prohibit yourself from doing something you may wish to do
How should a tender process be conducted? (3) - Even if a tender process contract exists, the principal can still conduct a proper tender evaluation provided it complies with the process
Codes of tendering - Australian Standard AS 4120-1994 Code of Tendering - Based on a number of ethical principles, including (1) Tendering at all levels in the construction industry shall be conducted honestly and in a manner that is fair to all parties involved
Codes of tendering - Australian Standard AS 4120-1994 Code of Tendering - Based on a number of ethical principles, including (2) Parties shall not engage in practices such as collusion on tenders, inflation of prices to compensate unsuccessful tenderers, secret commissions, or any other such improper arrangements
Codes of tendering - Australian Standard AS 4120-1994 Code of Tendering Sets out obligations of principal and obligations of tenderers
Part IV Competition and Consumer Act 2010 (Cth) – restrictive trade practices • Applies to corporations • Prohibits cartel conduct, including: Price fixing Bid rigging
Part IV Competition and Consumer Act 2010 (Cth) – restrictive trade practices - Prohibits ‘contracts, arrangements or understandings’ between competitors which would have the effect of... substantially lessening competition
Created by: Asher - S
 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards