Save
Upgrade to remove ads
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

CTS 1

QuestionAnswer
What are the four teams that comprise the overall Project Team? Owner, Design, Installation, and Management
who would make up the Management Team? Developer, Construction Manager, and Building Management Agency
Which groups represent the generic roles that are important to the Project process? Project Manager, Designers, and Installers
Which project characteristics must be considered in order to determine which method is best suited for a particular project? Schedule, Size, Type, Complexity, and Procurement Requirements
which is an important aspect of funding that has a direct impact on the project process and design/installation? Technical Support Funding
Whether a construction project is large or small, which milestones must be achieved in a typical schedule? Programming, Building Design, AV Bid, and Move-In
What type of project is a typical Consultant-Led Design-Bid-Build contract structure good for? Long term projects with extended project cycles
What is the risk in using an OFE/Integrator Installed contract structure? System and infrastructure design and facility functionality may suffer
What are some of the important project scope and size considerations in selecting an AV provider? Current Workload, Company Credentials, and Employee Experience
What type of document typically includes Project Size Requirements, Corporate Profile, Team Personnel, and Warranty Response Time? RFQ
What is one of the disadvantages of contracting the AV integrator to the electrical subcontractor? More layers of responsibility and communication
When conducting a complete project bid process, what milestone follows the issuing of the RFP? Pre-Bid Meeting
Under what circumstances would you likely use an A305-1986 form? Scoring responses to an RFQ
What is the ideal way to contract an AV integrator? Directly to the Owner
The process of identifying the activities that end-users need to perform, and developing the functional descriptions of your systems is referred to as: Needs Analysis
What is the main task of the third Step of the Program Phase of a Project? Conducting program meetings
What should be included in the written Program Report? A conceptual and functional system description
After writing the Program Report, what is the next step in the Program Phase? Distributing the Report
The Program Report's executive summary should contain An overview of the project, systems, and any special issues
During the Program Phase, what types of documentation should be reviewed during the Review of Existing Documentation and Facilities step? Architectural, Organizational, and Technical
What is the correct order of the steps involved in the Design Phase of a project? Kick-off meeting, establishing the infrastructure, developing the design package, and reviewing the package
Step Two of the Design Phase of a project is characterized by which of the following options? Conceptual and Schematic Design
During the Design Phase of a project, during which step is the fabrication, installation, functional, and quality intent determined? Step Three: Develop the Design Package
which team members best reflect the team of participants during the Review step of a project's Design Phase? Architect, Program Manager, Owner, and End-User
Which part of the Construction Specifications Institute's three-part format covers Installation Standards, Adjustments, and User Training? Execution
When including GUI Layouts into the Design Documents, which of the following should also be included for optimum usability? Button-by-Button Functionality
During the Design Phase, what are three major coordination efforts that need to be addressed between the AV designer and the base building design team? Space Planning, Data/Telecom, and Administrative Coordination
Which group comprises the principal participants in Construction Phase activities? Architect, General Contractor, and AV Integrator
At what point of the Construction Phase does AV System Testing occur? At the end
During the Construction Phase of a project, which step always follows AV System Testing? Site Installation
What is the last step of the Construction Phase? Finalizing Documentation
During the Construction Phase, what is likely to happen if a product is suddenly discontinued? A Request for Change is triggered
During the Construction Phase, what is the last thing to do before site installation? Conduct equipment and systems testing
Verification and Optimization are two concepts that are applied during System Commissioning to ensure that: The design intent has been met
During which step in the System Commissioning and Training Phase is the final checklist for the complete installation generated? Generate the Punch List
What are the primary functions of Step Four of the System Commissioning and Training Phase of a project? Inspecting, Testing and Aligning
When is the best time to train users during the System Commissioning and Training Phase of a project? After the punch list has been generated
Which type of warranty typically involves additional costs and adjustments? Service
If a system meets the original design, fulfills the needs of the end-user, and remains in proper working order, what will be the result? A successful project
Program Phase Steps 1.Review existing documentation and facilities 2.Benchmark Comparable facilities 3.Conduct the program Meetings 4.Write the program report 5.Distribute the report 6.Approve the program report as a basic system design
Design Phase Steps 1.Start design phase with a kick off meeting 2.Establish the infrastructure 3.developing the AV system design package 4.Making the most of the review
Construction Phase steps 1.Construction Kick off meeting 2.Preparing for Submittals 3.Procuring the AV equipment 4.Preparing the site 5.Preassembling and testing the AV system 6.Site installation 7.Finalizing the documentation
System Commissioning and training 1.Perform Preliminary test on the Completed system installation 2.Generate the punch list 3.Establish substantial completion 4.inspect test and align 5.Train users 6. Sign off and start warranty period
ICIA Acronym for the International Communications Industries Association, IncĀ®; the trade association representing the professional audiovisual industry worldwide, also associated with its annual tradeshow, InfoComm
(FF&E): Furniture, fixtures and equipment
BRI: acronym for Basic Rate Interface; a single ISDN line that utilizes two 56 or 64Kbps channels plus one 16Kbps data channels. see also PRI and ISDN
describe the PAL video standard? 625 lines, 25 frames per second, interlaced
Which is considered the better method of Y/C separation? Comb filtering
Bandwidth limiting a video signal is achieved by Encoding the video information.
The horizontal scan rate for PAL and SECAM is 15,625 Hz.
What is the output of the chroma decoder when its input is the chrominance signal? The component color difference signals, R-Y and B-Y
Bandwidth limiting of full bandwidth video is necessary for Broadcast within the existing standards that permit black and white video
What is the output of the chroma decoder? I and Q (or u and v) signals
In order to playback a video, what other signal MUST a videotape also have? Control track
digital storage standards? D-5 Digital8 DVD
The sampling ratio of 4:2:2 tells us that the Luminance is sampled at full bandwidth and the R-Y, B-Y are sampled at half
Name three other items that can be recorded along with the video signal onto videotape." Audio, control track, and timecode.
Another name for a fixed resolution display is Fixed matrix.
Which imaging technology requires no external lamp? Emissive
A VGA display is____ pixels. 640 by 480 pixels.
Created by: 1388243246
 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards