click below
click below
Normal Size Small Size show me how
EGB382 (Week 1)
Construction Project Lifecycle
Question | Answer |
---|---|
Conception - The conception phase of a civil construction project is the initial stage where the project idea is... | conceived and developed. In this phase, the project concept is explored, and the feasibility of the project is assessed |
Conception – Key Activities 1) Project identification and scoping | In this stage, the project idea is identified, and the scope of the project is defined. The project concept is refined and developed, and initial assessments are made of its feasibility and potential benefits |
Conception – Key Activities 2) Feasibility study - A feasibility study is conducted to determine whether the project is viable and can be completed within the available resources, time, and budget. The study examines... | the technical, economic, financial, social, and environmental aspects of the project |
Conception – Key Activities 3) Preliminary design - Based on the feasibility study, preliminary design work is undertaken to develop a concept design for the project. This includes determining the required... | engineering and architectural aspects of the project, such as the materials and construction methods to be used |
Conception – Key Activities 4) Cost estimation | An estimate of the total cost of the project is prepared, including construction costs, labour costs, and other associated expenses |
Conception – Key Activities 5) Stakeholder engagement | Engagement with relevant stakeholders, such as local communities, regulatory authorities, and other interested parties, is carried out to identify any concerns or issues that may affect the project |
Conception – Key Activities 6) Risk assessment | A risk assessment is conducted to identify potential risks that may affect the project's success, such as natural disasters or delays due to unforeseen circumstances |
Conception – Key Activities 7) Project charter | The project charter is created, outlining the project's objectives, scope, timeline, budget, and stakeholders involved |
Planning & Design | The planning and design phase of a civil construction project typically follows the conception phase and involves developing detailed plans and designs for the project |
Planning & Design – Key Activities 1) Detailed design | In this stage, the project's engineering and architectural plans are developed in detail, including the exact dimensions, materials, and construction methods to be used |
Planning & Design – Key Activities 2) Environmental impact assessment | An assessment is carried out to identify any potential environmental impacts that the project may have and to develop strategies to minimize or mitigate these impacts |
Planning & Design – Key Activities 3) Permitting and regulatory compliance | The project team works with regulatory agencies to obtain necessary permits and ensure compliance with local, state, and federal regulations |
Planning & Design – Key Activities 4) Cost estimating and budgeting | A detailed cost estimate is developed based on the detailed design, and a project budget is created |
Planning & Design – Key Activities 5) Construction schedule | A construction schedule is developed that outlines the timeline for the project, including start and completion dates for different phases of the project |
Planning & Design – Key Activities 6) Risk management | A risk management plan is developed to identify and manage potential risks that may arise during the construction process |
Planning & Design – Key Activities 7) Quality control | A plan for ensuring the quality of the construction work is developed, including inspections, testing, and documentation |
Planning & Design – Key Activities 8) Procurement and contracting | Procurement and contracting plans are developed to ensure that materials and services are obtained in a timely and cost-effective manner |
Planning & Design – Key Activities 9) Project management plan | A project management plan is developed that outlines the roles and responsibilities of all project team members, as well as communication protocols, reporting requirements, and other project management procedures |
Construction | The construction phase of a civil construction project involves the actual physical construction of the project as per the plans and designs developed during the planning and design phase |
Construction – Key Activities 1) Mobilization | The project team mobilizes to the site, including contractors, workers, and equipment |
Construction – Key Activities 2) Site preparation | The site is prepared for construction, including clearing and grading the land, installing temporary facilities, and setting up safety measures |
Construction – Key Activities 3) Construction work | The actual construction work begins, including laying foundations, building structures, installing utilities, and landscaping |
Construction – Key Activities 4) Material management | Materials and equipment are delivered to the site and managed efficiently to ensure that they are used appropriately and according to the project schedule |
Construction – Key Activities 5) Quality control and assurance | Quality control measures are implemented to ensure that the construction work meets the required standards, including inspections, testing, and documentation |
Construction – Key Activities 6) Safety management | Safety protocols are implemented to ensure the safety of workers and the public during construction |
Construction – Key Activities 7) Progress monitoring | The project's progress is monitored regularly, and adjustments are made as necessary to keep the project on schedule and within budget |
Construction – Key Activities 8) Communication and coordination | Communication and coordination among project team members are maintained to ensure that the construction work is carried out smoothly and efficiently |
Construction – Key Activities 9) Closeout and commissioning | Once the construction work is complete, the project is commissioned, and a final inspection is carried out before the project is handed over to the owner |
Commissioning & Turnover | The commissioning & turnover phase of a civil construction project is the final stage of the project and involves testing and verifying that all systems and components are working correctly and as per the design intent |
Commissioning – Key Activities 1) System testing | All systems and components of the project, such as electrical, mechanical, plumbing, and HVAC, are tested to ensure that they are functioning correctly |
Commissioning – Key Activities 2) Performance testing | Performance testing is carried out to ensure that the project is meeting its design criteria and specifications, including energy efficiency and environmental performance |
Commissioning – Key Activities 3) Operational readiness | Operational readiness tests are carried out to ensure that the project is ready for occupancy and meets all safety and regulatory requirements |
Commissioning – Key Activities 4) Documentation | All project documentation, including operations and maintenance manuals, safety procedures, and testing records, are prepared and handed over to the owner |
Commissioning – Key Activities 5) Training | The project team provides training to the owner's staff on the operation and maintenance of the project's systems and components |
Commissioning – Key Activities 6) Final inspection | A final inspection is carried out to ensure that the project meets all regulatory requirements and is ready for occupancy |
Commissioning – Key Activities 7) Project closeout | The project is formally closed out, including financial closeout, final payments to contractors and suppliers, and other administrative tasks |
Renewal | The renewal phase of a civil construction project involves the rehabilitation or renovation of existing infrastructure or facilities to extend their useful life and maintain their performance |
Renewal – Key Activities 1) Condition assessment | A condition assessment is carried out to determine the extent of the renovation or rehabilitation work required and to identify any potential risks or issues |
Renewal – Key Activities 2) Design development | Based on the condition assessment, a detailed design is developed that outlines the renovation or rehabilitation work to be carried out, including materials, methods, and construction details |
Renewal – Key Activities 3) Permitting and regulatory compliance | The project team works with regulatory agencies to obtain necessary permits and ensure compliance with local, state, and federal regulations |
Renewal – Key Activities 4) Cost estimating and budgeting | A detailed cost estimate is developed based on the detailed design, and a project budget is created |
Renewal – Key Activities 5) Construction work | The renovation or rehabilitation work is carried out, including repair or replacement of systems and components, upgrades, and modifications |
Renewal – Key Activities 6) Material management | Materials and equipment are delivered to the site and managed efficiently to ensure that they are used appropriately and according to the project schedule |
Renewal – Key Activities 7) Quality control and assurance | Quality control measures are implemented to ensure that the renovation or rehabilitation work meets the required standards, including inspections, testing, and documentation |
Renewal – Key Activities 8) Safety management | Safety protocols are implemented to ensure the safety of workers and the public during construction |
Renewal – Key Activities 9) Progress monitoring | The project's progress is monitored regularly, and adjustments are made as necessary to keep the project on schedule and within budget |
Renewal – Key Activities 10) Closeout and commissioning | Once the renovation or rehabilitation work is complete, the project is commissioned, and a final inspection is carried out before the project is handed over to the owner |
Demolition | The demolition phase of a civil construction project involves the dismantling and removal of existing infrastructure or facilities |
Demolition – Key Activities 1) Planning and permitting | A detailed demolition plan is developed that outlines the sequence of demolition, methods, and equipment to be used. The project team also obtains the necessary permits and complies with local, state, and federal regulations |
Demolition – Key Activities 2) Hazardous material removal | Any hazardous materials, such as asbestos or lead-based paint, are removed from the site before demolition |
Demolition – Key Activities 3) Salvage and recycling | Salvageable materials, such as metal or concrete, are removed from the site and recycled or repurposed as appropriate |
Demolition – Key Activities 4) Demolition work | The demolition work is carried out, including dismantling structures, breaking up concrete, and removing debris |
Demolition – Key Activities 5) Material management | Debris and waste are removed from the site and managed efficiently to minimize environmental impact |
Demolition – Key Activities 6) Safety management | Safety protocols are implemented to ensure the safety of workers and the public during demolition |
Demolition – Key Activities 7) Site restoration | The site is restored to its original condition or prepared for new construction as required |
Demolition – Key Activities 8) Closeout and documentation | The project is formally closed out, including final inspections, financial closeout, and other administrative tasks. Documentation is also prepared to ensure compliance with regulatory requirements |
Circular Economy 1) | Circular economy in construction refers to an economic system where resources are kept in use for as long as possible, waste is minimized, and materials are reused or recycled at the end of their life |
Circular Economy 2) | This approach contrasts with the traditional "take-make-dispose" linear model of resource consumption, where resources are extracted, used to create products, and then discarded as waste |
Circular Economy in Construction 1): In the context of construction, the circular economy involves designing buildings and infrastructure that can be easily disassembled and reused or recycled at the end... | of their life. This may involve using materials that are easier to recycle, such as timber or steel, or designing buildings that can be easily deconstructed and their materials repurposed |
Circular Economy in Construction 2): | Other strategies for implementing a circular economy in construction include reducing waste during construction by using prefabricated elements, reusing existing buildings or materials, and using materials that have a low environmental impact |
Circular Economy in Construction 3): The circular economy in construction has the potential to reduce the environmental impact of the construction industry, which is a significant contributor to... | greenhouse gas emissions and resource consumption. It can also provide economic benefits by creating new business opportunities in the recycling and repurposing of materials |