click below
click below
Normal Size Small Size show me how
PMP Chapter 4
Question | Answer |
---|---|
All change requests must be documented and pass through a (BLANK) | CCS or Change Control System |
A condition, rule or procedure that restricts a project manager's options is a (BLANK). | Constraint |
(BLANK) is documentation of a how a project will be planned, executed, monitored and controlled and then closed. | Project Management Plan |
What are the four inputs to the Project Management Plan? | - Project Charter - Outputs from the other project management processes - Enterprise Environmental Factors - Organizational Process Assests |
Inspecting work that has been corrected after an initial failed effort is known as (BLANK) | Defect Repair Review |
The formal verification of the contract completeness by the vendor and the performing organization is known as (BLANK) | Contract Closure |
The Project Management Plan 4.2.3.1 provides what three project baselines? | Scope, Schedule and Cost |
A project manager is responsible for ensuring that there is a (BLANK) for a change, prior to submission into the integrated control system. | Need. Without evidence and detailed need for a change no submission should occur. |
The Change Management Plan is included in the (BLANK) and documents how changes will be monitored and controlled. | Project Management Plan |
A subsystem of the overall project management, the (BLANK) manages how changes are submitted reviewed and tracked. It also focuses documenting the physical characteristics and changes to those characteristics. | Configuration Management System |
True or False - A program manager directs the project work if a project falls within their program. | False - In a program, the program manager assigns the project manager authority to direct program work. |
(BLANK) serves as part of organizational process assets and provides historical information for future projects. | Lessons Learned Documentation |
(BLANK) is the process of measuring the performance of a project against what was planned. | EVM or Earned Value Management |
True or False - Risk responses are included in the project charter. | False - While high level risks maybe included the responses to those risks are NOT included in the project charter |
There are two primary approaches used by an organization to decide which projects to pursue. What are they? | Mathematical Model or Benefits/Comparison Model |
The Project Statement of Work or SOW is formed in the Project Charter. The SOW must include 3 items. What are they? | 1. Business Need 2. Product Scope Description 3. Strategic Plan |
What is the formula for Present Value? | PV = FV/(1+i)^n |
What is the formula for Future Value? | FV = PV(1+i)^n |
When change enters a project what two documents must be updated? | The scope baseline and the change log |