Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

PMP Chapter 4

QuestionAnswer
All change requests must be documented and pass through a (BLANK) CCS or Change Control System
A condition, rule or procedure that restricts a project manager's options is a (BLANK). Constraint
(BLANK) is documentation of a how a project will be planned, executed, monitored and controlled and then closed. Project Management Plan
What are the four inputs to the Project Management Plan? - Project Charter - Outputs from the other project management processes - Enterprise Environmental Factors - Organizational Process Assests
Inspecting work that has been corrected after an initial failed effort is known as (BLANK) Defect Repair Review
The formal verification of the contract completeness by the vendor and the performing organization is known as (BLANK) Contract Closure
The Project Management Plan 4.2.3.1 provides what three project baselines? Scope, Schedule and Cost
A project manager is responsible for ensuring that there is a (BLANK) for a change, prior to submission into the integrated control system. Need. Without evidence and detailed need for a change no submission should occur.
The Change Management Plan is included in the (BLANK) and documents how changes will be monitored and controlled. Project Management Plan
A subsystem of the overall project management, the (BLANK) manages how changes are submitted reviewed and tracked. It also focuses documenting the physical characteristics and changes to those characteristics. Configuration Management System
True or False - A program manager directs the project work if a project falls within their program. False - In a program, the program manager assigns the project manager authority to direct program work.
(BLANK) serves as part of organizational process assets and provides historical information for future projects. Lessons Learned Documentation
(BLANK) is the process of measuring the performance of a project against what was planned. EVM or Earned Value Management
True or False - Risk responses are included in the project charter. False - While high level risks maybe included the responses to those risks are NOT included in the project charter
There are two primary approaches used by an organization to decide which projects to pursue. What are they? Mathematical Model or Benefits/Comparison Model
The Project Statement of Work or SOW is formed in the Project Charter. The SOW must include 3 items. What are they? 1. Business Need 2. Product Scope Description 3. Strategic Plan
What is the formula for Present Value? PV = FV/(1+i)^n
What is the formula for Future Value? FV = PV(1+i)^n
When change enters a project what two documents must be updated? The scope baseline and the change log
Created by: lapetti
Popular Computers sets

 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards