PMP-BTV Word Scramble
|
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.
Normal Size Small Size show me how
Normal Size Small Size show me how
Question | to design qualityAnswer |
6 Processes in Project Time Management | Define Activities, Sequence activities, Estimate Activity Resource, Estimate Activity Duration, Develop Schedule, Control Cost |
Scheduling Methodology definition | defines the rules and approaches for scheduling processes |
2 common scheduling methodologies. | CPM (Critical Path Methodology) & Critical Chain |
What plan documents the project time management processes and their associated tools and techniques | schedule management plan |
Schedule Management plan is a subsidary of or contained in what plan? | Project Management Plan |
3 Inputs to Define Activities Process | Scope Baseline, EEF, OPA |
3 outputs of Define Activities Process | Activity List, Activity Attributes, Milestone List |
5 Inputs to Sequence Activities Process | Activity List, Activity Attributes, Milestone List, Project Scope Statement, OPA |
2 Outputs from Sequence Activities? | Project Schedule Network Diagrams, Project Document Updates |
5 Inputs to Estimate Activity Resources? | Activity List, Activity Attributes, Resource Calendars, EEF,OPA |
3 Outputs of Estimate Activity Resources? | Activity resource requirements, Resource Breakdown Structure, Project Document Updates |
7 Inputs to Estimate Activity Durations | Activity List, Activity Attributes, Activity Resource Requirements, Resource Calendars, Project Scope Statement, EEF, OPA |
2 outputs of Estimate Activity Durations | Activity Duration Estimates, Project Docuiment Updates |
9 Inputs to Develop Schedule? | Activity List, Activity Attributes, Project Schedule Network Diagrams, Activity Resource Requirements, Resource calendars, Activity Duration Estimates,Project Scope Statement, EEF, OPA |
4 Outputs of Develop Schedule | Project Schedule, Schedule baseline, Schedule Data, Project Document Updates |
4 Inputs to Control Schedule | Project Management Plan, Project Schedule, Work performance information, OPA |
5 Outputs of Control Schedule | Work Performance Measurements, OPA updates, Change Requests, Project Management Plan Updates, Project Document Updates |
Tools and Techniques used in Define Activities | -Decomposition -Rolling Wave Planning -Template -Expert Judgement |
Tools & Techniques used in Sequence Activities | -Precedence Diagramming method (PDM) -Dependency Dettermination -Applying leads and lags -Schedule network templates |
Tools and Techniques used in Estimate Activity Resource | -Expert Judgement -Alternatives Analysis -Published Estimating Data -Bottom up estimating -Project Management Software |
Tools and Techniques used in Estimate Activity Durations | -Expert Judgement -Analagous Estimating -Parametric Estimating -Three Point Estimates -Reserve analysis |
Tools & Techniques used in Develop Schedule | -Schedule network Analysis -Critical path method -Critical chain method -Resource leveling -What if scenarion analysis -Applying leads anfd lags -Schedule compression -Scheduling tool |
Tools & Techniques in Control Schedule | -performance reviews -variance analysis -project management software -resource leveling -what if scenarion analysis -adjusting leads and lags -schedule compression -scheduling tool |
What is PDM? | Precedence Diagramming Method |
What is a common technique of PDM? | Activity on Node (AON) |
Three dependencies (types of logic) with AON | Mandatory - Hard logic Discretionary - Soft logic External - Depends on input from outside the project activities |
Four relationship Types | -SS -FS -SS -SF |
Define Lag | modification of a logical relationship that directs a delay in the successor activity |
define Lead | modification in a logical relationship that allows an acceleration of the successor activity |
6 Estimate Activity Durations Methods | -One Time -Three Point -Monte Carlo -Analogous Estimating (Top-Down) -Bottom up -Parametric |
Rolling Wave Planning | More detail to near term deliverables while future at a more general level |
3 Schedule Formats? | -Bar Chart -Milestone chart -Network Diagram with Dates |
Wait inserted between tasks | Lag |
Amount of time a task can be delayed without delaying project | Float or slack |
Which Scheduling term considers resource limitations and adjusts the schedule to work within those functions | Critical Chain Methods |
2 Schedule compression techniques | -Crashing -Fast tracking |
3 Processes in Project Cost Management | -Estimate Costs -Determine Budget -Control Costs |
6 Inputs to Estimate Costs | -Scope Baseline -Project Schedule -Human Resources Plan -Risk Register -EEF -OPA |
9 Tools and Techniques of Estimating costs | -Expert Judgement -Analogous estimating -Parametric estimating -Bottom up estimating -Three point estimates -Reserve analysis -Cost of quality - Project Management Estimating software -Vendor bid analysis |
3 outputs of Estimate Costs | -Activity Cost Estimates -Basis of Estimates -Project Documetn Updates |
7 Inputs to Determine Budget | -Activity Cost Estimates -Basis of estimates -Scioe Baseline =Project Baseline -Resource Calendars -Contacts -OPA |
5 Tools and Techniques of Determine Budget | -Cost Aggregation -Reserve analysis -Expert Judgement -Historical relationships -Funding Limit reconciliation |
3 outputs of determine budget | -Cost performance Baseine -Project funding requirements -projet document updates |
4 Inputs to Control costs | -Project Management Plan -Project funding Requirements -Work performance information -OPA |
6 Tools and techniques to Control Costs | -Earned value management -Forecasting -To-Complete Performance Indes (TCPI) -Performance reviews -Variance analysis -Project management software |
6 outputs of Control costs(Exapmle of each as well) | -Work performance measurements(CV,SV,CPI,SPI for WBS components) -Budget Forecasts(Calculated EAC value or Bottom Up Estimation )-OPA Updates(Variance cause, documented lessons) -Change requests -Project management plan updates -Project document updates |
What process enables PM to know if they should include funds above estimate to reduce risk of overruns & what are these funds called | Reserve analysis, Contingency reserves |
What happens to Contingency as project/Activity progresses? | Decreases |
What are three elements of Scope Baseline | -Scope Statement -WBS -WBS Dictionary |
6 Elements of Scope Statement | -Product Description -acceptance criteria -key deliverables -project boundaries -assumptions -constraints about project |
Define Basis of estimates | Basis of estimate is basically a definition of how the estimates were derived. |
Define Cost Aggergation | Aggregate cost estimates for work packages in WBS |
Reserve analysis can establish what? | Contingency reserves & Management reserves |
Define Management reserves | budgets reserved for unplanned changes to project scope and cost |
What is funding limit reconciliation? | determining if the variance between funding limits and planned expenditures warrents rescheduling |
What is the authorized time-phased BAC? | CPB - Cost performance baseline |
Shape of CPB? | S-Curve |
Define EVM | Earned Value Management - Method of performance measurement that integrates project scope, cost and schedule measurements to help the project management team asses and measure project performance |
Three deminsions of EVM | -Planned Value -Earned Value -Actual Cost |
Define PV | Planned Value - authorized budget assigned to the work to be accomplished |
Total project PV (Two terms) | PMB - Performance measurement baseline BAC - Budget at completion |
Define EV | Earned Value - value of workperformed expressed in terms of the approved budget assigned to the work activity or WBS component. |
Define AC | Actual Cost- total cost actually incurred and recorded on accomplishing work performed for an activity |
Define SV & Give formula | Schedule Variance - measure of schedule performance on a project |
When does SV always = 0 | When project is completed |
Define CV & Give formula | Cost Variance - Measure of cost performance of project. EV-AC |
Define SPI and give formula | Schedule Performance Index - Measure of progress achieved compared to progress planned -SPI=EV/PV |
Define CPI and give formula. | Cost performance Index - Measure of the value of the work completed to the actual cost or progress made -CPI=EV/AC |
What is the most important EVM metric | CPI |
What does the CPI represent in relation to 1 | CPI <1 = cost overrun CPI>1 = cost underrun |
What does PM do when BAC is no longer viable | Develop forecasted EAC |
What is EAC based on? | Actual cost of work performed plus and ETC (Estimate to Complete) -EAC=ETC(Bottom up) +AC |
EAC forecast for ETC work performed at the budgeted rate - formula and when used | EAC = AC + BAC - EV (Only use when assuming improved project performance determined by risk analysis) |
EAC forecast for ETC work performed at present CPI - formula and when used | EAC=BAC/Cumulative CPI -(when assuming consistent performance |
EAC forecasts for ETC work considering both SPI and CPI- formula and when used | AC+[(BAC-EV)/Cumulative CPI * Cumulative CPI] (Used when negative cost performance and requirement to meett firm requirement) |
TCPI - Formula and definition | BAC:(BAC-EV)/(BAC-AC) EAC: (BAC-EV)/(EAC-AC) - Projection of cost performance that must be achieved on remaining work to meet a specific management goal |
3 types of analysis for performance reviews under EVM | earned value performance trend analysis Variance analysis |
In variance analysis, what are CV and CPI used to asses? | Magnitude of variation to the cost baseline |
3 Processes in Quality Management | -Plan Quality -Perform Quality Assurance -Perform Quality Control |
What is involved in Performing Quailty Assurance | Auditing quality requirements and the results from Quality control measurements |
Quality Vs Grade | Defect Rate Vs Feature list |
7 Inputs to Plan Quality | -Scope Baseline -Stakeholder Register -Cost Performance Baseline -Schedule Baseline -Risk Register -EEF -OPA |
9 Tools and Techniques to Plan Quality | -Cost benefit analysis -Cost of quality -Control Charts -Benchmarking -Design of experiments -Statistical Sampling -Flowcharting -Proprietary quality management methodologies -Additional Quality planning tools |
5 outputs of planning quality | -Quality management plan -quality metrics -quality checklists -Process improvement plan -project document updates |
4 Inputs to Perform Quality Assurance | -Project management plan -Quality Metrics -Work performance information -quality control measurements |
3 tools and techniques to perform quality assurance | -paln quality and perfiorm QC tools and techniques -Quality audits -Process analysis |
4 outputs of perform quality assurance | -OPA Updates -Change requests -Project management plan update -Project documents |
7 Inputs to Perform Quality Control | -Project management Plan -Quality Metrics -Quality Checklist -ork percormance measurements -Approved Change requests -Deliverables -OPA |
10 tools and techniques to Perform QC | -Cuase and effect diagram -Control charts - Flowcharting -Histogram -Pareto Chart -Run Chart -Scatter Diagram -Statistical sampling -Inspection -Apprioved Change Request review |
7 outputs to Perform QC | QC Measurements -Validated Changes -Validated deliverables -OPA Updates -Change REquests -PMP Updates -Project document updates |
2 divisions of COQ | -Cost of conformance -cost of nonconformance |
Who bears responsibility of quality | entire organization |
define quality in relation to requirements | degree to which a set of inherent characteristics xatisfies requirements |
Acuracy vs precision | Accuracy = hitting target, precision= consistency |
define plan quality and when is it performed? | process of identifying quality requirements and documenting how project will maintain compliance. Throughout project |
List and define 3 types of qulity costs | -Prevention - upfront costs to design quality -Appraisal - Costs associated with evaluating whether the programs or processes meet the requirements |
3 elements of a HR Plan | -Roles and Resp -Staffing Mgt Plan -Org charts |
who is responsible for managing triple constraints | Senior mgt |
3 types of responsibility chart | -RAM - Shows who does what, but not when -Resource histogram/Staffing mgt plan - Resource allocated/time period -Gantt Chart - Shows when staff is allocated to task |
RAM uses What to assign responsibilities | RACI |
Common format of staffing management plan | histogram |
Schedule variance (Formula) | SV=EV-PV |
Cost Variance(Formula) | CV=EV-AC |
Cost Performance Index (Formula) | CPI=EV/AC |
Schedule Performance Index | SPI=EV/PV |
EAC Formula | AC+Estimate to complete |
EAC if past variances are expected to be atypical | EAC=AC+BAC-EV |
EAC if past variances are expected to be typical | EAC=BAC/Cumulative CPI |
To calculate the budget that will be required to increase the amount of resources to a level that will allow the work to be completed in the remaining time: | EAC = AC + [(BAC - EV) / (cumulative CPI x cumulative SPI)] |
To-complete performance index (TCPI) When using the BAC | TCPI = (BAC - EV) / (BAC - AC) |
To-complete performance index (TCPI) When using the EAC | TCPI = (BAC - EV) / (EAC - AC) |
Conduct that results in physical harm or creates intense feelings of fear, humiliation, manipulation, or exploitation in another person is defined as harassment by the PMI code. | False |
PMI Definition of harassment |
Created by:
btvennen
Popular Management sets