LEED-NC Word Scramble
|
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.
Normal Size Small Size show me how
Normal Size Small Size show me how
Question | Answer |
"SS" stands for? | Sustainable Sites |
The intent is to control sediment during construction. | SS Pre 1: Construction Activity Pollution Prevention. |
What are the options of SS Pre 1? | Opt. 1: Erosion sediment control plan to meet the 2003 EPA General Construction Permit(GCP); Option 2 is an erosion control plan to meet or local codes, whichever is more stringent; Some strategies include BMP's (silt fencing, mulching, seeding, basins) |
What type of restricted sites can you not develop on per SS1: Site Selection? | 1. Farmland as defined by USDA 7CFR (currently used as farmland & able to support crop & animal farming); 2. previously undeveloped w/in 5' above FEMA flood |